March 4th, 2010
What a nice cozy environment to work in as we near the end of a very long, very cold, and very snowy winter. The first order of business was sawing through the concrete for the addition of another bathroom. After installing insulation in the ceiling, Nathan, Jeremy, and Chantry started with the framing. Soon after, Alleghany Highlands Mechanical installed the duct work and David Lightner, of Lightner's Electric in Monterey, installed the rough-in electrical systems. We began yesterday installing the sheetrock as the plumber finished making all of his connections and will continue with hanging and finishing over the next couple of weeks.
Nathan works to install sheetrock nailers
Chantry shoveling a path to the basement door
tent set up to contain the concrete dust from sawing into the floor
ceiling framing begins
Chantry sawing for Nathan and Jeremy
wall framing begins
framing complete
sheetrock begins
|